Development Projects • National Showcase
Audited physical and financial lifecycle tracking across all electoral wards. Inspect Bill of Quantities (BQ), milestone completions, site inspection reports, and geocoded locations.
| Code | Project Name | Ward | Sector | FY | Allocated (KES) | Spent (KES) | Progress | Status | Action |
|---|---|---|---|---|---|---|---|---|---|
| PRJ-211-2025-005 | Solar-Powered Borehole Water Reticulation & Storage Tank at Central Maragoli | Central Maragoli | Water & Environment | 2024/2025 | 4,500,000.00 | 4,500,000.00 | 100% | Substantial / Physical Completion | View |
| PRJ-211-2025-003 | Construction of Sub-County Police Post & Chiefs Administrative Complex at Mungoma | Mungoma | Security & Governance Infrastructure | 2024/2025 | 7,200,000.00 | 5,760,000.00 | 85% | Site Handed Over & Civil Works Active | View |
| PRJ-211-2025-002 | Construction of Tuition Classrooms & Modern Sanitation Block at Lugaga-Wamuluma Primary School | Lugaga-Wamuluma | Education & Academic Infrastructure | 2024/2025 | 6,800,000.00 | 6,800,000.00 | 100% | Substantial / Physical Completion | View |
| PRJ-211-2025-001 | Construction of Modern Science Laboratories & Classrooms at Central Maragoli Secondary School | Central Maragoli | Education & Academic Infrastructure | 2024/2025 | 9,500,000.00 | 9,500,000.00 | 100% | Substantial / Physical Completion | View |
| PRJ-209-2025-005 | Solar-Powered Borehole Water Reticulation & Storage Tank at Isukha West | Isukha West | Water & Environment | 2024/2025 | 4,500,000.00 | 4,500,000.00 | 100% | Substantial / Physical Completion | View |
| PRJ-209-2025-003 | Construction of Sub-County Police Post & Chiefs Administrative Complex at Isukha North | Isukha North | Security & Governance Infrastructure | 2024/2025 | 7,200,000.00 | 5,760,000.00 | 85% | Site Handed Over & Civil Works Active | View |
| PRJ-209-2025-002 | Construction of Tuition Classrooms & Modern Sanitation Block at Isukha East Primary School | Isukha East | Education & Academic Infrastructure | 2024/2025 | 6,800,000.00 | 6,800,000.00 | 100% | Substantial / Physical Completion | View |
| PRJ-209-2025-001 | Construction of Modern Science Laboratories & Classrooms at Isukha Central Secondary School | Isukha Central | Education & Academic Infrastructure | 2024/2025 | 9,500,000.00 | 9,500,000.00 | 100% | Substantial / Physical Completion | View |
| PRJ-216-2025-005 | Solar-Powered Borehole Water Reticulation & Storage Tank at Kapkateny | Kapkateny | Water & Environment | 2024/2025 | 4,500,000.00 | 4,500,000.00 | 100% | Substantial / Physical Completion | View |
| PRJ-216-2025-003 | Construction of Sub-County Police Post & Chiefs Administrative Complex at Chesikaki | Chesikaki | Security & Governance Infrastructure | 2024/2025 | 7,200,000.00 | 5,760,000.00 | 85% | Site Handed Over & Civil Works Active | View |
| PRJ-216-2025-002 | Construction of Tuition Classrooms & Modern Sanitation Block at Chepyuk Primary School | Chepyuk | Education & Academic Infrastructure | 2024/2025 | 6,800,000.00 | 6,800,000.00 | 100% | Substantial / Physical Completion | View |
| PRJ-216-2025-001 | Construction of Modern Science Laboratories & Classrooms at Cheptais Secondary School | Cheptais | Education & Academic Infrastructure | 2024/2025 | 9,500,000.00 | 9,500,000.00 | 100% | Substantial / Physical Completion | View |