Construction of Assistant County Commissioner (ACC) Office Complex at Sikhendu

PRJ-KMN-2025-004 Security & Governance Infrastructure • Sikhendu Ward • FY 2024/2025 Site Handed Over & Civil Works Active
Last officially verified on site by M&E Officer: May 20, 2025 • Assessed: Satisfactory - Minor Observations • Verified Physical Progress: 45%
Physical Progress
45%
Approved Budget
KES 7,000,000
Allocated (Current FY)
KES 7,000,000
Disbursed to PMC
KES 4,000,000
Verified Spent
KES 2,800,000
Absorption Rate
70.0%

8-Point Project Transparency Profile

Kenya Constitution Art. 35 Verified

Public transparency index answering the 8 core citizen accountability dimensions mandated by Section 23 of the NG-CDF platform guidelines.

1. What is being built?
Construction of Assistant County Commissioner (ACC) Office Complex at Sikhendu (Security & Governance Infrastructure)
2. Where is it located?
Sikhendu Ward • Kiminini Constituency NG-CDF (GPS: 0.912400, 34.992100)
3. Who benefits?
National Government Administration (NGAO) (~24,000 citizens)
4. How much does it cost?
Budget: KES 7,000,000 • Contract: KES 7,000,000
5. How much has been disbursed?
Disbursed: KES 4,000,000 • Spent: KES 2,800,000 (Absorption: 70.0%)
6. What is current status?
Site Handed Over & Civil Works Active • Verified progress: 45%
7. What bottlenecks exist?
No active execution bottlenecks
8. What documents are available?
Engineering drawings & BOQ summary registered

Project Description & Scope of Works

Administrative block featuring ACC executive office, conference boardroom, registry archives, and holding cells to bring government civil services closer to citizens.

Bill of Quantities (BQ) Summary

Substructure: KES 1.5M, Walling: KES 2.8M, Roofing & Ceiling: KES 1.6M, Security Perimeter: KES 1.1M

Construction Milestones & Civil Works Schedule

Foundation & Ground Slab
Weight Contribution: 25%
Verified Complete
Mar 30, 2025
Superstructure Walling to Ring Beam
Weight Contribution: 35%
Verified Complete
Jun 15, 2025
3
Roofing Installation & Ceiling Plaster
Weight Contribution: 25%
Target: In Progress
4
Finishes, Glazing & Security Doors
Weight Contribution: 15%
Target: In Progress

Visual Site Documentation Timeline

Site photographs being compiled by the M&E field team.

Project Statutory Documents & BOQs

No official engineering drawings or BOQ files uploaded for this project yet.

Field Monitoring & Inspection Reports

Inspection Date: May 20, 2025 • Verified Progress: 45%
Satisfactory - Minor Observations
Observations: Routine site verification for Construction of Assistant County Commissioner (ACC) Office Complex at Sikhendu. Works aligned with approved architectural BQs.
Snags / Defects Identified: Ensure perimeter drainage channel is cleaned prior to handover.

Execution Challenges & Mitigation Actions

No active contractual or physical execution bottlenecks logged for this project.