PRJ-KMN-2025-002 Education & Academic Infrastructure • Sirende Ward • FY 2024/2025 Site Handed Over & Civil Works Active
Last officially verified on site by M&E Officer: May 20, 2025 • Assessed: Satisfactory - Minor Observations • Verified Physical Progress: 75%
Physical Progress
75%
Approved Budget
KES 7,500,000
Allocated (Current FY)
KES 7,500,000
Disbursed to PMC
KES 6,000,000
Verified Spent
KES 4,800,000
Absorption Rate
80.0%

8-Point Project Transparency Profile

Kenya Constitution Art. 35 Verified

Public transparency index answering the 8 core citizen accountability dimensions mandated by Section 23 of the NG-CDF platform guidelines.

1. What is being built?
Construction of Modern Outpatient & Maternity Complex at Sirende Dispensary (Education & Academic Infrastructure)
2. Where is it located?
Sirende Ward • Kiminini Constituency NG-CDF (GPS: 0.952310, 34.981204)
3. Who benefits?
Sirende Dispensary (~8,500 citizens)
4. How much does it cost?
Budget: KES 7,500,000 • Contract: KES 7,500,000
5. How much has been disbursed?
Disbursed: KES 6,000,000 • Spent: KES 4,800,000 (Absorption: 80.0%)
6. What is current status?
Site Handed Over & Civil Works Active • Verified progress: 75%
7. What bottlenecks exist?
No active execution bottlenecks
8. What documents are available?
Engineering drawings & BOQ summary registered

Project Description & Scope of Works

Expanding maternal healthcare access for rural mothers through a 12-bed maternity ward, laboratory testing room, immunization clinic, and solar backup system.

Bill of Quantities (BQ) Summary

Substructure: KES 1.8M, Superstructure: KES 3.2M, Electrical & Solar: KES 1.4M, Plumbing & Sanitary: KES 1.1M

Construction Milestones & Civil Works Schedule

Site Clearing & Foundation Casting
Weight Contribution: 20%
Verified Complete
Nov 15, 2024
Superstructure Walling & Lintel Beams
Weight Contribution: 30%
Verified Complete
Feb 28, 2025
Roofing & Truss Fabrication
Weight Contribution: 25%
Verified Complete
May 10, 2025
4
Solar Installation & Interior Finishing
Weight Contribution: 25%
Target: In Progress

Visual Site Documentation Timeline

Site photographs being compiled by the M&E field team.

Project Statutory Documents & BOQs

No official engineering drawings or BOQ files uploaded for this project yet.

Field Monitoring & Inspection Reports

Inspection Date: May 20, 2025 • Verified Progress: 75%
Satisfactory - Minor Observations
Observations: Routine site verification for Construction of Modern Outpatient & Maternity Complex at Sirende Dispensary. Works aligned with approved architectural BQs.
Snags / Defects Identified: Ensure perimeter drainage channel is cleaned prior to handover.

Execution Challenges & Mitigation Actions

No active contractual or physical execution bottlenecks logged for this project.