Kiminini Constituency NG-CDF

Construction of Twin Science Laboratories at Kiminini High School

PRJ-KMN-2025-001 Education & Academic Infrastructure • Kiminini Ward • FY 2024/2025 Substantial / Physical Completion
Last officially verified on site by M&E Officer: May 20, 2025 • Assessed: Excellent - Meets Engineering BQ Standards • Verified Physical Progress: 100%
Physical Progress
100%
Approved Budget
KES 9,500,000
Allocated (Current FY)
KES 9,500,000
Disbursed to PMC
KES 9,500,000
Verified Spent
KES 9,500,000
Absorption Rate
100.0%

8-Point Project Transparency Profile

Kenya Constitution Art. 35 Verified

Public transparency index answering the 8 core citizen accountability dimensions mandated by Section 23 of the NG-CDF platform guidelines.

1. What is being built?
Construction of Twin Science Laboratories at Kiminini High School (Education & Academic Infrastructure)
2. Where is it located?
Kiminini Ward • Kiminini Constituency NG-CDF (GPS: 0.985612, 34.954201)
3. Who benefits?
Kiminini High School (~1,450 citizens)
4. How much does it cost?
Budget: KES 9,500,000 • Contract: KES 9,500,000
5. How much has been disbursed?
Disbursed: KES 9,500,000 • Spent: KES 9,500,000 (Absorption: 100.0%)
6. What is current status?
Substantial / Physical Completion • Verified progress: 100%
7. What bottlenecks exist?
No active execution bottlenecks
8. What documents are available?
Engineering drawings & BOQ summary registered

Project Description & Scope of Works

Fully equipped physics, chemistry, and biology laboratories outfitted with gas piping hoods, fire suppression, laboratory workbenches, and acid-resistant sinks to boost STEM learning.

Bill of Quantities (BQ) Summary

Substructure: KES 2.2M, Superstructure: KES 3.8M, Roofing: KES 1.5M, Interior Fittings & Gas Hoods: KES 2.0M

Construction Milestones & Civil Works Schedule

Substructure Excavation & Foundation
Weight Contribution: 15%
Verified Complete
Sep 15, 2024
Superstructure Walling & Ring Beam
Weight Contribution: 25%
Verified Complete
Nov 20, 2024
Structural Steel Trusses & Prepainted Iron Roofing
Weight Contribution: 20%
Verified Complete
Jan 15, 2025
Laboratory Gas Piping, Sinks & Electrical Fittings
Weight Contribution: 25%
Verified Complete
Mar 10, 2025
Final Inspection, Painting & Snag Commissioning
Weight Contribution: 15%
Verified Complete
Apr 28, 2025

Visual Site Documentation Timeline

Site photographs being compiled by the M&E field team.

Project Statutory Documents & BOQs

No official engineering drawings or BOQ files uploaded for this project yet.

Field Monitoring & Inspection Reports

Inspection Date: May 20, 2025 • Verified Progress: 100%
Excellent - Meets Engineering BQ Standards
Observations: Routine site verification for Construction of Twin Science Laboratories at Kiminini High School. Works aligned with approved architectural BQs.
Snags / Defects Identified: None. Substantial completion achieved.

Execution Challenges & Mitigation Actions

No active contractual or physical execution bottlenecks logged for this project.