Drilling and Solar Reticulation of High-Yield Borehole at Waitaluk Market

PRJ-KMN-2025-003 Water & Environment • Waitaluk Ward • FY 2024/2025 Site Handed Over & Civil Works Active
Last officially verified on site by M&E Officer: May 20, 2025 • Assessed: Satisfactory - Minor Observations • Verified Physical Progress: 60%
Physical Progress
60%
Approved Budget
KES 5,500,000
Allocated (Current FY)
KES 5,500,000
Disbursed to PMC
KES 4,500,000
Verified Spent
KES 3,300,000
Absorption Rate
73.3%

8-Point Project Transparency Profile

Kenya Constitution Art. 35 Verified

Public transparency index answering the 8 core citizen accountability dimensions mandated by Section 23 of the NG-CDF platform guidelines.

1. What is being built?
Drilling and Solar Reticulation of High-Yield Borehole at Waitaluk Market (Water & Environment)
2. Where is it located?
Waitaluk Ward • Kiminini Constituency NG-CDF (GPS: 1.014520, 34.921400)
3. Who benefits?
Waitaluk Market & Surrounding Schools (~6,200 citizens)
4. How much does it cost?
Budget: KES 5,500,000 • Contract: KES 5,500,000
5. How much has been disbursed?
Disbursed: KES 4,500,000 • Spent: KES 3,300,000 (Absorption: 73.3%)
6. What is current status?
Site Handed Over & Civil Works Active • Verified progress: 60%
7. What bottlenecks exist?
No active execution bottlenecks
8. What documents are available?
Engineering drawings & BOQ summary registered

Project Description & Scope of Works

150-metre geophysical borehole drilling, test pumping, solar-powered submersible pump installation, 20,000-litre elevated storage tank, and community water kiosk.

Bill of Quantities (BQ) Summary

Geological Survey & Hydro Drilling: KES 2.5M, Solar Pumping Unit: KES 1.8M, Steel Tower & Tank: KES 1.2M

Construction Milestones & Civil Works Schedule

Hydrogeological Survey & Drilling
Weight Contribution: 35%
Verified Complete
Mar 20, 2025
Submersible Solar Pump Installation
Weight Contribution: 25%
Verified Complete
May 15, 2025
3
Elevated Tank Tower Construction
Weight Contribution: 25%
Target: In Progress
4
Distribution Pipes & Public Water Kiosk
Weight Contribution: 15%
Target: In Progress

Visual Site Documentation Timeline

Site photographs being compiled by the M&E field team.

Project Statutory Documents & BOQs

No official engineering drawings or BOQ files uploaded for this project yet.

Field Monitoring & Inspection Reports

Inspection Date: May 20, 2025 • Verified Progress: 60%
Satisfactory - Minor Observations
Observations: Routine site verification for Drilling and Solar Reticulation of High-Yield Borehole at Waitaluk Market. Works aligned with approved architectural BQs.
Snags / Defects Identified: Ensure perimeter drainage channel is cleaned prior to handover.

Execution Challenges & Mitigation Actions

No active contractual or physical execution bottlenecks logged for this project.