Kiminini Constituency NG-CDF

Perimeter Wall, Ablution Block & 120 Desks at Hospital Primary School

PRJ-KMN-2025-005 Education & Academic Infrastructure • Hospital Ward • FY 2024/2025 Substantial / Physical Completion
Last officially verified on site by M&E Officer: May 20, 2025 • Assessed: Excellent - Meets Engineering BQ Standards • Verified Physical Progress: 100%
Physical Progress
100%
Approved Budget
KES 4,500,000
Allocated (Current FY)
KES 4,500,000
Disbursed to PMC
KES 4,500,000
Verified Spent
KES 4,500,000
Absorption Rate
100.0%

8-Point Project Transparency Profile

Kenya Constitution Art. 35 Verified

Public transparency index answering the 8 core citizen accountability dimensions mandated by Section 23 of the NG-CDF platform guidelines.

1. What is being built?
Perimeter Wall, Ablution Block & 120 Desks at Hospital Primary School (Education & Academic Infrastructure)
2. Where is it located?
Hospital Ward • Kiminini Constituency NG-CDF (GPS: 1.002100, 34.975400)
3. Who benefits?
Hospital Primary School (~920 citizens)
4. How much does it cost?
Budget: KES 4,500,000 • Contract: KES 4,500,000
5. How much has been disbursed?
Disbursed: KES 4,500,000 • Spent: KES 4,500,000 (Absorption: 100.0%)
6. What is current status?
Substantial / Physical Completion • Verified progress: 100%
7. What bottlenecks exist?
No active execution bottlenecks
8. What documents are available?
Engineering drawings & BOQ summary registered

Project Description & Scope of Works

Security perimeter masonry wall safeguarding 900 pupils from highway traffic, modern 16-door waterborne VIP latrines, and provision of 120 standardized 3-seater wooden desks.

Bill of Quantities (BQ) Summary

Perimeter Wall: KES 2.2M, Ablution Block: KES 1.5M, Wooden Desks: KES 800,000

Construction Milestones & Civil Works Schedule

Perimeter Wall Masonry & Razor Wire
Weight Contribution: 40%
Verified Complete
Oct 15, 2024
VIP Ablution Block Construction
Weight Contribution: 35%
Verified Complete
Dec 20, 2024
Desk Carpentry, Painting & Handover
Weight Contribution: 25%
Verified Complete
Feb 25, 2025

Visual Site Documentation Timeline

Site photographs being compiled by the M&E field team.

Project Statutory Documents & BOQs

No official engineering drawings or BOQ files uploaded for this project yet.

Field Monitoring & Inspection Reports

Inspection Date: May 20, 2025 • Verified Progress: 100%
Excellent - Meets Engineering BQ Standards
Observations: Routine site verification for Perimeter Wall, Ablution Block & 120 Desks at Hospital Primary School. Works aligned with approved architectural BQs.
Snags / Defects Identified: None. Substantial completion achieved.

Execution Challenges & Mitigation Actions

No active contractual or physical execution bottlenecks logged for this project.